The roofs, windows, building paper, and cavity battens for Lot 1, 2, 4, 5, and 6 have been installed, and the Council inspection for the Cavity Wrap has passed in full.
The installation of the external walls for Lot 4 has been completed, and the cladding inspection has passed.
The amendment plan for Lot 3 has been approved by the Council.
2. 1 Weldene Ave, Glenfield Project
Project Progress:
223/224C has been received, and all technical documents have been reviewed by the Council engineer and registered in the New Zealand Land Information Centre.
The lawyer has received all the approved technical documents and has completed the application process for the title.
The 10-year Master Builder Guarantee Certificate has been received.