Newland Capital Management Ltd

Newland Capital exclusive project information – February

1. Project: Harbor View

Project Address:

37 West Harbor Dr, West Harbor

Project Owner:

Newland No.1 Limited Partnership

Project Progress:

  • 1.Despite three rare and severe storms with strong winds and heavy rain in February, construction work at the site has proceeded according to plan, with all foundation and retaining wall construction work completed.
  • Due to thorough preparations, the damage caused by the hurricane and heavy rain to the site was minimal, with only a small loss, except for the part of the fence that collapsed due to construction and the storm at the boundary with the neighbors, which has been replaced with a new fence ahead of schedule.
  • The construction of the framework and private drainage has begun.

2. Project:Weldene Ave, Glenfield

项目动态:

  • EACC has received.
  • The CCC review has been completed, and the review fee has been paid. The CCC can be obtained now.